Main Street Construction Project in Valentine

Next year’s work has started. When this project was let for bidding, the construction scheduling had a start date of 04/01/2022 with a contract time of 215 working days. Phase 3 work was scheduled to be completed in 2023.  Today is working day 88.

 Midlands contracting is continuing utilities work between A Street and Hwy 20. Water Mains and Sanitary Sewer Mains are being placed. All Phase 3 work.

Paulsen Construction will continue placing sidewalks on the 200 block of Main Street into next week. The 2nd Street intersection is to be open to cross traffic soon and some mainline roadway is scheduled to be placed this week.

 IES Construction company continues working on conduit and wiring for Traffic Signals and street lighting. A lot more work needed.