Paulsen Construction will continue concrete placement for driveways for the area of HWY 20 to A Street. Sidewalks to follow. A Street and B Street intersections have been placed and will be opened in the near future.
A second Paulsen crew has placed the ADA compliant pedestrian crossings at 3rd & Main and will continue work on the pedestrian crossings at 2nd & Main.
Barnes construction continues construction of various project items.
IES will continue to place conduit and footings for Street Lights and Traffic Signals. The HWY 20 Traffic signal will be the first installed with others to follow.
Paulsen construction (Prime contractor), is checking on scheduling additional IES workers to install street lighting.