Starting today, a project begins in Todd County from the intersection of U.S. Highway 18 and U.S. Highway 83 to the east approximately one mile to Cheyenne Road.
Work on this project, which runs from Mission to the community of Antelope, consists of replacement of the existing roadway lighting system.
During the project, traffic will be controlled by lane closures and flaggers.
The existing roadway lighting in this area will be turned off today. It is anticipated that the new roadway lighting system will be operational mid to late June 2023.
Muth Electric of Mitchell, SD is the prime contractor on this $492,000 project. The project is scheduled for completion on Friday, June 30, 2023.